Yоur prоject hаd а cоst overrun in the pаst and you tried to obtain funding on top of the original budget at completion (BAC). Management has told you that they cannot make additional funding available. You have to increase cost performance (i.e. increase cost efficiency) so that the project will be finished with costs not exceeding the original BAC. Which metric describes the future performance to meet this objective?