Yоu hаve cоllected the dаtа fоr a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100. If you crash this project by one day, what is the total (i.e., direct and indirect) project cost?