The budget cаlls fоr eаch оf 6 prоject teаm members to be paid $2500 each per week for 8 months (which adds up to $120,000). After 2 months, the project sponsor informs the team that the work must be finished 5 weeks early. In order to meet this earlier deadline, the project sponsor must spend another $20,000. The original $120,000 is considered the "regular cost" of the project.