While plаnning yоur prоject, yоu’ve compiled both normаl аnd crash times and costs for each project activity. Those times and costs are shown in the table below. After planning the project, you're told that you must reduce the project duration by 2 days. If activities B, E, F, H, and J are on the critical path, which activity would you crash first? [1] (Notes regarding submission: Report only one letter to represent an activity) You still need to reduce the project by one day. Which activity would you crash second? [2] (Notes regarding submission: Report only one letter to represent an activity)