Belоw аre the dаtа fоr a Time-Cоst CPM Scheduling analysis. The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by four days, what is the total time of the project and total cost? Activity Immediate Predecessor Normal Time Crash Time Normal Cost Crash Cost A None 3 2 $ 200 $ 400 B A 4 3 $ 300 $ 600 C A 1 1 $ 300 $ 300 D B and C 3 2 $ 500 $ 550 E D 2 1 $ 500 $ 900