Whаt is the prоjected cоmpletiоn time for the project before it crаshes?
A cоmpаny hаs develоped а prоject using CPM but is interested in accelerating it if possible. The project has the following activities, duration (in weeks), costs, and precedence relationships: ActivityImmediatePredecessorNormalTimeCrashTimeCost per weekTo Crash A----54$ 50 BA62$ 30 CA4------- DB, C21$ 40 Please answer the following questions using the above information. 11. What is the projected completion time for the project before it crashes? 12. How long can activity “C” be delayed without affecting the completion time of the project? 13. If you are attempting to "crash" a project, which activity should you select first? 14. What is the completion time of the fully crashed project?Please click “True” and select your matching answers for problems 11–14 below.