Mаtch the questiоns listed belоw with the аpprоpriаte answers for the following scenario: In response to the COVID-19 pandemic, Shands Hospital at UF has decided to expand its hospital room capacity with an additional 80 upgraded patient care rooms to the main building. Rooms are approximately 500 square feet (sq ft) in size and are expected to cost $465/sq ft fully equipped at buildout. During construction, the plan is for 4,000 sq ft (space equivalent to 8 rooms) to be completed (on average) each month for 10 months. The estimated cost of the entire project is $18,600,000. You are the University of Florida construction PM responsible for managing the design-build contractor for the new addition. The table below represents the status of your project at the end of Month 6 as reported to you by the contractor; you have verified the report against project progress and believe it to be accurate: