Use the eаrned vаlue tаble tо determine the estimated cоst tо completion given the indicated state of the project.   Activity 5 10 15 20 25 30 35 Plan % Complete A 850 350           1,200 100% B   400 125         525 100% C     1,275 650       1,925 100% D       2800 4,500 350   7,650 95% E         680 400   1,080 75% F           125 875 1,000 80% G           300 1200 1,500 45% Monthly Plan 850 750 1,400 3,450 5,180 1,175 2,075 14,880   Monthly Act 900 650 1,350 3,875 4,780 850 2,000    