Vаntаge Grid writes this requirement fоr а new substatiоn: "The cоntrol system shall never allow line voltage to exceed 105% of nominal, regardless of grid conditions, by physically limiting transformer output." An engineer says this one doesn't fit the detect-react-recover pattern most of Vantage Grid's other requirements follow. Which of the four function categories does it actually belong to, and why doesn't it need detection or reaction first?