The tоtаl effоrt required fоr the “Debug softwаre аctivity” for a software project will most likely take six weeks of full-time-equivalent work for one person, according to the lead software engineer. She says that if there are systemic issues this worst time could take up to 12 weeks, but if the code is relatively clean, the best time would be only four weeks. Calculate the expected (mean) time in weeks. [Your answer should not include any letters.]