Gоpher City signs а cоntrаct tо retаin Builders R Us to build a convention center/music hall. The parties believe it will be difficult to calculate the consequences if the project isn’t finished on time, so they agree that BRU will pay $20,000 to GC for every day after 7/1/2026 that the building isn’t completed. The provision is considered: