Fоr this exercise, use the infоrmаtiоn below. The criticаl pаth (CP) is A, C, & D, and the time/duration is in weeks: PERT Activities.png 1. What is the probability of completing the project in 19 weeks (TS = 19)?  2. What is the probability of completing the project in 22 weeks (TS = 22)?  3. What is the probability of completing the project in 28 weeks (TS = 28)?  Note: for full credit, you must show your calculations! z = (TS - TE)/Square Root of Sum of Variances Use the z-score table below (as a hint, if the z-score you calculated is not in the table below, the z-score you calculated is incorrect!):  Z-Score  Probability  -3.0  0.001  -2.0  0.023  -1.0  0.159  0.0  0.500  1.0  0.841  2.0  0.977  3.0  0.998   