Given the following network diagram (assume finish to start…

Given the following network diagram (assume finish to start relationships and duration in days): Indicate the critical path(s) using the appropriate activity letter sequence: [CP] What is the shortest time to complete this project (in days)? [time] Which path has the highest Total Float or Slack? [path] For the path(s) identified as the Critical Path, what is the Total Float (in days)? [TF]