Consider the assembly line balancing problem described in th…

Consider the assembly line balancing problem described in the table below. Assume cycle time is 25. Task Task Time Immediate Predecessor Positional Weight A 5 – [pwA] B 10 A [pwB] C 5 A [pwC] D 15 B,C [pwD] E 5 D [pwE] F 15 D [pwF] G 5 E [pwG] H 10 F,G [pwH] (a) (6 points) Calculate the positional weight for each task (add to table above). (b) (6 points) Assign tasks to workstations according to the Ranked Positional Weight (RPW) heuristic. If a workstation is empty, just put N/A in the box. Workstation 1 tasks: [ws1] Workstation 2 tasks: [ws2] Workstation 3 tasks: [ws3] Workstation 4 tasks: [ws4] (c) Answer yes or no to the following questions. (2 points) Does task C dominate task D? [cd] (2 points) Does task B dominate task C? [bc] (2 points) Does task F dominate task E? [fe] (4 points) Did the RPW heuristic produce the optimal line balance? [opt]

Upload a PDF of your answers and cheat sheet here. Once you…

Upload a PDF of your answers and cheat sheet here. Once you begin uploading your exam file, you may not continue working on the exam. Your submission must reflect only work completed prior to accessing your device. Any evidence of work performed after accessing your device or during the upload process may be treated as an academic integrity violation. You are responsible for allowing enough time to scan and upload your exam before the timer expires. The quiz will automatically submit when time runs out.