In the Reading Pipe case, Jacob and Youngs v. Kent, the cont…

In the Reading Pipe case, Jacob and Youngs v. Kent, the contractor installed the wrong brand of piping throughout the building that was specifically stated in the contract. Once it was discovered, it was far too late in the construction process to replace all the pipes without a substantial extra cost to the contractor. What was the resolution of the case when the contractor was sued by his client for breach of contract?