A Contractor is using a wheeled loader with the bucket size…

A Contractor is using a wheeled loader with the bucket size of 2.5 CY to carry the moist loam. The density of moist loam is 2,200 lb/LCY, and the fill factor is 1.05. The static tipping load of the loader is 15,600 lb. The fixed travel time is 0.8 min. The average speed for hauling and return is 3 mph and 6 mph, respectively. The travel distance is 450 ft. The operation efficiency is 45 min/hour. The contractor estimates hourly cost for the wheeled loader; the ownership cost is $28/hour, the operating cost is $30/hour, and the operator wage is $29.5/hour. What is the maximum capacity per cycle? What is the loader’s productivity? What is the estimated unit cost in $/LCY of the loader to work on the job?

You are working for a contractor that has a contract for con…

You are working for a contractor that has a contract for construction of a new hospital. As part of the project, you need to remove the soil for the construction of the basement and foundation for a parking garage. From the project plans, you know that 5,000 bank cubic yards must be excavated and that 1,200 compacted cubic yards will be required to backfill the completed foundation. You plan to stockpile the soil needed for backfill on site and haul the excess soil to a disposal site. The average haul distance is estimated to be 500 ft. with an 8% average uphill grade. The contractor had the soil tested and determined that the bank density is 2,900 pounds per cubic yard, the loose density is 2,250 pounds per cubic yard, and the compacted density is 3,150 pounds per cubic yard. What is the percent swell for the soil? What is the percent shrinkage for the soil? How many bank cubic yards should be stockpiled to be used for backfill operation? How many loose cubic yards of soil should be hauled away to the disposal site?