A contractor has a project involving the construction of a s…

A contractor has a project involving the construction of a small manufacturing plant. The contractor has selected a borrow site and has decided to use 27-cubic yard dump trucks to haul the needed fill material. The contractor has decided to use a hydraulic excavator with a shovel attachment to load the trucks. The excavator has expected productivity as 422cy/hr at 100% efficiency, and the truck cycle time excluding loading is 0.48hr. The job site operation efficiency is assumed as 0.8. Please answer the next two questions. What is the expected fleet production if only 6 trucks are available to the fleet?