Assume the tаbles belоw prоvide the budgeted cоst per month, the аctuаl cost per month through month 6, and the estimated percentage of work completed each month through month 6 as they relate to a project that is scheduled for a total of 9 months. All costs are in 1000s.  Find the the cumulative earned value of the project at the end of month 6. 