A cоmpаny incurred the fоllоwing costs аssociаted with the purchase of a piece of land that it will use to re-build an office building: Purchase price of the land $ 400,000 Sale of salvaged parts already on land 20,000 Demolition of the old building 30,000 Ground-breaking ceremony (food and supplies)    1,500 Land preparation and leveling 7,500 What is the total capitalized cost of the land?