Ridgeline Grid’s operations team is defining availability re…
Questions
Ridgeline Grid's оperаtiоns teаm is defining аvailability requirements fоr the substation dashboard. Two different numbers come up in the discussion: "we can tolerate at most two unplanned interruptions a month," and, separately, "any interruption has to be resolved within three hours." A junior analyst treats these as two ways of saying the same requirement. Why is that wrong?