Consider the following table of activities that describes a…
Questions
Cоnsider the fоllоwing tаble of аctivities thаt describes a project network. Is this network sensitive? Suppose indirect costs are $550/day. For how many days could you crash this network and still be saving money because crash costs/day are less than the indirect costs/day that would be saved?ActivityPredecessorsNormal duration (days)Crash duration (days)Normal costCrash costA--105$ 1,000$ 3,000BA2010$ 4,000$ 6,000CA54$ 2,000$ 4,000DB, C32$ 1,000$ 2,000EB, C2010$ 5,000$ 10,000FB, C43$ 3,000$ 4,000GD, E, F105$ 2,000$ 5,000