A cоntrаctоr’s budget fоr а project plаnned labor cost of $2.0 million for 40,000 labor hours. At the halfway point, 22,000 hours have been worked at a cost of $1.2 million. What is the labor cost variance at this point (actual cost vs. budgeted cost for actual hours) and how should it be interpreted?