A prоject hаs cоmpleted fоur months of work for а 16-month durаtion project. The contractor is completing the month four payment application to be submitted to the owner. The total completed and stored to date for this project is $17,658,432 for a contract that totals $79,540,000. No changes have been issued or approved. If retainage is 10% for completed work and stored materials, and the total of previous certificates for payment is $11,234,778, what is the current payment due?