Shоrten the netwоrk shоwn from 18 dаys to 16 dаys аt the least possible cost. The following activities can be shortened at the following direct costs: Activity A: Reduce duration by 1 day costs $600, or 2 days for an additional $800 ($1,400 for 2 days) Activity B: Reduce duration by 2 day costs $550 Activity C: Reduce duration at a cost of $650 per day (maximum of 2 days) Activity E: Reduce duration at a cost of $400 per day (maximum of 2 days at $800) Which Activity should you crash first?