Kelly Jackson is assigned to a software development project…

Questions

Kelly Jаcksоn is аssigned tо а sоftware development project that will start in the near future and is currently tailoring the PMBOK processes to satisfy the project’s specific needs. Kelly wants to introduce a new process, “Identify Key Deliverables”, to the existing six project scope management processes. Although she understands that project deliverables identification is already in the PMBOK scope management processes, she believes that having a dedicated process will stress the importance of determining and agreeing to key project deliverables. The best position for the new “Identify Key Deliverables” process should be between which of the following two processes?