Yоu hаve cоllected the dаtа fоr a Time-Cost CPM Scheduling model analysis. The time is in days and the project "direct costs" are given below.The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days the total indirect costs are $400, 15 days they will be $250, 14 days they will be $200, and 13 days they will be $100. At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs)? Activity Immediate Predecessor Normal Time Crash Time Normal Cost(Direct) Crash Cost(Direct) A None 3 2 $ 300 $ 400 B A 3 3 $ 100 $ 100 C A 1 1 $ 200 $ 200 D B and C 3 2 $ 400 $ 550 E D 2 1 $ 500 $ 900 F E 3 3 $ 200 $ 200 G F 2 2 $ 100 $ 100