A Six Sigmа prоject teаm is wоrking tо reduce errors in а financial reporting process. The root cause analysis showed a significant difference between departments. The team is in the Improve phase and evaluating several solutions. The table below summarizes scores against decision criteria for the solutions. CRITERIA AND WEIGHT Cost CTQ Impact Ease of Implementation Customer Satisfaction SOLUTION 3 4 2 1 TOTAL SCORE A 5 5 2 3 (a) B 1 2 1 4 (b) C 3 2 1 2 (c) Scoring: 1 = Worse and 5 = Better What is the total score for solution A? [sa] What is the total score for solution B? [sb] What is the total score for solution C? [sc] Which solution should the team pick? [select] (enter A, B or C)